The expansion of Tubelite’s assembly, warehousing and distribution operations will be complete by mid-June.

The Company will be increasing its plant space by twenty percent. It will also increase the number of shipping docks by fifty-percent to accommodate its growing needs.

The assembly operation will relocate to the west-end of the facility beginning on June 8th with a completion date of June 11th.

The warehouse and distribution operation will complete its relocation the following week, June 14th through June 18th.

A large portion of the relocation will occur over the weekends involved, minimizing any disruption to production and shipping. All order entry and shipping scheduling has been adjusted to incorporate the downtime required for the relocation.